The installation of dry-type epoxy encapsulated transformer is the same as that of other machines, and requires standard installation. What are the issues that need to be paid attention to during the installation of dry-type transformers? Let's take a look at the main specifications for the installation of dry-type transformers.
Handover test for dry-type epoxy encapsulated transformer installation specification
The test adjustment and body inspection results of the power dry-type transformer and its accessories must comply with the construction specifications.
Defects such as crack damage and enamel damage are strictly prohibited on the surface of high and low pressure porcelain parts.
The installation specification of the dry-type transformer should be accurate, the surface of the body should be clean, and the paint should be complete.
The dry-type transformer installation specification shall have anti-smashing and anti-collision measures for the high and low voltage bushings and epoxy resin castings of the dry-type transformer in place.
The dry-type transformer body should be kept clean, and the paint surface has collision damage. After the dry-type transformer is in place, protective measures should be taken to prevent iron parts from falling into the coil.
When working under the conditions of dry-type transformer installation specifications, the operator shall not step on the dry-type transformer, and bring a tool bag to prevent tool materials from falling into and damaging the dry-type transformer.
Operating conditions for dry-type epoxy encapsulated transformer installation specifications
Construction drawings and technical data are complete and correct.
The basic construction of the civil engineering has been completed, and the elevation, size, structure and strength of the embedded parts meet the design requirements.
The roof and roof spraying is completed, the roof has no water leakage, and the doors, windows and glass are well installed.
The indoor rough ground work is completed, the site is cleaned up, and the road is smooth.
The above are the main specifications and main installation procedures for common dry-type transformer installations for your reference.